The new facility & refurbishment will provide the hospital with a new Ultra Clean Theatre with 6 bed 1st stage recovery & and an 11 bed 2nd stage recovery.
The programme will last a total of 20 weeks on site with the Theatre and 1st stage recovery being handed over within 14 weeks.
The existing hospital was developed from an 18 Century Manor House and has therefore made it priority to closely match the existing finishes for the new extension to achieve a successful planning application.
New Royal Eye Infirmary at Plymouth Hospital sees key role for Innovative FLEX financing from…
MTX has worked nationally for over two decades, serving the NHS with the construction of…
Diagnostic and imaging centre contract at Frimley Park Hospital in Surrey awarded to Modern Methods…
Second phase of a state of the art surgical hub at Clatterbridge Hospital on the…
The state-of-the-art Elective Orthopaedic Surgery Centre being built at Colchester Hospital features in a TV…
MTX has completed a project to deliver four state-of-the-art operating theatres at the Royal Bolton…